Area cordoned off for new building
Piling commenced
Piling and civils in progress
Piling continuing....
New building foundations in progress
Concrete pour for building slab
Excavating for west utility service slab
Rebar work for west utility service slab
Rebar, shuttering and ducts for west service slab
Concrete poured and setting for west service slab
Steel frame being erected
Steel frame complete
Kingspan cladding installed
Sub-station being installed
Power cabling
Power cabling to sub-stations
Sub-stations installed
EDPM roof installation
Air-con pipe-work on roof
Air-con condensers on roof
Close-up of roof condensers
Front loading platform (side on)
Front loading platform (front on)
Internal stairs to second floor
Automatic Mains Failure Switches
Generator installation
Generators in situ
Generators in situ (front on)
Tray-work and cabling
Generator fuel tanks
Modular room panel erection
Room 1 raised floor installation
Sub-floor rack power cabling
Air-con pipe-work
Power distribution equipment
Room 1 nearing completion